As demand for artificial intelligence (AI) chips continues to outstrip supply, NVIDIA is facing increasing shipment pressure, resulting in significantly longer lead times for its products. This not only affects the data center product line but also extends to workstation graphics cards, which are facing supply constraints. As for gaming graphics cards, rumors suggest that NVIDIA's supply will decrease by another 20% to 30% in the fourth quarter.
According to TrendForce, sources revealed that the lead time for B300 orders ranges from 26 to 40 weeks, while GB300 is between 14 and 26 weeks. The delivery period for RTX PRO series GPUs has now exceeded 26 weeks. Given the current supply situation, most new orders placed in the past two quarters are expected to be fulfilled only by Q2 or Q3 of 2027, or even later. This has led NVIDIA to continuously reduce shipments of GeForce RTX 50 series GPUs, and the next-generation GeForce RTX 60 series GPUs will also face delays.
Fortunately, despite the longer lead times for new orders, shipments of existing AI servers and workstations equipped with RTX PRO series GPUs, as well as local AI systems like the DGX Station workstation and RTX Spark AI PC, are largely proceeding as scheduled.
Strong AI demand is also reshaping DRAM production priorities, causing DRAM manufacturers to prioritize server-grade DRAM products. This limits GDDR7 production capacity, ultimately driving up prices and further squeezing the supply of gaming graphics cards. Under these circumstances, the GeForce RTX 60 series, originally scheduled for release in late 2027, may be delayed until 2028, and AMD's next-generation Radeon gaming graphics cards will face similar delays.